Update activity areas

Activity areas are the spatial building blocks of a short-term plan in XECUTE. Each area defines where a specific activity—such as mining, drilling, or blasting—will occur. Once created, an activity area becomes a scheduled task in the Gantt chart, where resources perform the work at defined production rates. Without activity areas, you can’t schedule or track progress.

Activity areas bridge the gap between design and execution. They allow you to translate operational intent into actionable tasks that reflect real-world conditions. You create them whenever you need to model work that isn’t yet represented in the schedule (for example, after rolling the schedule forward or when new grade control data becomes available).

You can create activity areas in two ways:

Frequency of creating activity areas

Create activity areas whenever you need to keep the schedule aligned with reality. Common scenarios include:

Before you begin

Check these prerequisites to avoid errors and rework: