Determining the scenario start point

Determining the scenario start point

Previous topic Next topic  

Determining the scenario start point

Previous topic Next topic  

When you make a change to your databases or schedule setup, XPAC will determine where it should set the scenario start point according to the impact of the change. The following table lists potential changes and the corresponding scenario start point that XPAC will use for the schedule recalculation.

Note

If the Main or Calendar database data is modified, manually or by XCM, you must manually change the scenario start point to Initial Status.

If you are not sure of the ramifications of a change that you make to your project, the safest thing to do is to set the Scenario Start Point to the earliest possible place, namely the Initial Status. By doing this all changes will be incorporated in the schedule.

Change to Database or Schedule Setup

Schedule Recalculation from:

Import data to Main database

Initial Status

Add/delete Main database structure

Initial Status

Change Main database data manually or via XCM

Must be done manually

Import data to Calendar database

First Schedule Period

Add/delete Calendar database structure

First Schedule Period

Change Calendar database data manually or via XCM

Must be done manually

Edit Activity name or mining direction

No recalculation required

Add/delete Activities or edit the zero test data fields

Initial Status

Change the Active Scenario

Initial Status

Edit the Mined Out Quantities list

Mined Out Quantities

Change the Calendar database or Calendar Reference for the Active Scenario

First Schedule Period

Change the Time Slicing options for the Active Scenario

First Schedule Period

Change the Productive Activities for the Active Scenario

Initial Status

Change the Non Productive Activities for the Active Scenario

First Schedule Period

Change the Preschedule Table used in the Active Scenario

Preschedule

Change any Roster used in the Active Scenario

First Schedule Period

Change any Roster Exceptions used in the Active Scenario

First Schedule Period

Change any Period Delays used in the Active Scenario

First Schedule Period

Change any Production Rates used in Active Scenario

First Schedule Period

Change any Target Details used in Active Scenario

First Schedule Period

Change any Input Path used in Active Scenario

Affected Time Period