XPAC Reference Guide

Select Period Range window

Select Period Range window

Previous topic Next topic  

Select Period Range window

Previous topic Next topic  

The Select Period Range window displays when you run a schedule or generate a Schedule Status plot. If required, you can change the default settings before proceeding.

1.Change the Current Scheduling Run (XPAC displays only the available start and finish periods specified in the active calendar database for the active scenario):
a.Select the Start Period to determine the starting point from which XPAC runs the schedule.
b.Select the Finish Period to determine the end point at which XPAC stops running the schedule.
2.Change the Recalculation Start Point. Either:
a.Change the Record Status to determine the point in the schedule at which to start recalculating. (You can specify a default value for this field. See ?Changing the scenario start point for more information); or
b.Select the Always start from Initial Status check box if you want the schedule to always start from the beginning.
3.If available, generate a Schedule Status Plot in addition the schedule:
a.Click the Display status plot check box. The drop-down list becomes available for selection.
b.Select a Schedule Status plot that you previously created.
c.Select a period from the Advance to Period drop-down list.
4.If required, deselect the Use Global Statistics Cache check box.
5.If available, select the check box for each report that you want to generate after XPAC has run the schedule. Otherwise, select the All check box to run all reports.
6.Click OK.

XPAC either:

runs the schedule for the active scenario; or
generates the spatial data plot.