After you run the Schedule Checker, XPAC generates an error report and displays it on the screen. This report lists the time periods over which the Schedule Checker has been run, the checks that have been performed (ie. Block Dependencies and/or Activity Precedences), and the record conflicts that have been identified.
For each record conflict, the activity and record name are listed for both the record in conflict and its "Unmined Precedence". The time period in which the record is scheduled is also reported. A record conflict will be classed as one of the following types.
• | Error - The Step was completed before one of its predecessors was started. |
• | Warning - The Step was started before one of its predecessors was completed. |
Once the Schedule Checker report is displayed, it can be printed by selecting File from the application menu and then Print from the drop down menu. Alternatively, the report can be previewed by selecting Print Preview from the pull down menu. The format of the report is predefined and cannot be modified.