This topic deals with mine status reports as available from the Schedule Reports menu option or toolbar button. You can also produce mine status reports with Analysis Reporting Module.
|
Use mine status reports to generate information about the status of main database records at a particular point in time.
You can:
• | Select a specific range of main database records for the report. |
• | Generated the report for the end of any time period, as well as at the end of each stage of schedule setup, namely initial status, mined out quantities or preschedule. |
• | Specify whether records which have been completely mined or are completely unmined are to be included in the report. |
• | Include database data fields in the report, representing the original, remaining, mined or inventory values. |