XPAC Reference Guide

Path View right-click options

Path View right-click options

Previous topic Next topic  

Path View right-click options

Previous topic Next topic  

There are a number of right-click options that you can use to interact with paths that display in the Path View. For example, you can insert a block into an input path, or specify which fields display in the data sheet.

Resource path right-click options

The table below describes the right-click options when you have selected a path to display in the Path View:

Option

Description

Insert Block

Opens the Insert Block window so that you can insert a block in the selected path.

Insert Stockpile

Lets you insert a stockpile into the selected path.
 
Note: This option is only active if you have set up stockpiles in your scenario.

Delete All Following Steps

Lets you delete all the following steps in the path from the point at which your cursor is positioned.

Delete All Following Stockpile Steps

Lets you delete all the following stockpile steps in the path from the point at which your cursor is positioned.

Path Fields

Lets you specify which fields to display in the data sheet (see Selecting fields to display in the data sheet for more information).

Navigate To

Lets you navigate to the selected block/s in another part of the product, for example, select:

Record in Main Database to view the record in the Main database
Record in Combined Output Path to view the record in the Schedule Combined Output Path window
Record in Dependency View to view the record in the Dependency Rule View
Record in Spatial Data View to open the Edit Spatial Data window so that you can view and/or edit the record's spatial data set, if required.

Selecting fields to display in the data sheet

Note

This right-click option only displays if you selected a resource path from the Settings toolbar.

1.Right-click the data sheet and select Path Fields.
2.Select fields to Add and Remove as required from the Displayed fields lists.
3.If required, reorder selected fields by selecting a field and clicking Move Up or Move Down.
4.If required, click Reset to revert your changes.
5.If required, create a new field:
a.Click New Field.
b.In the Database Fields list, select a field.
c.Click OK.
6.If required, select a field type, for example, Database value.
7.Click OK.

The selected fields display in the data sheet.

Mined Out Quantities or Preschedule right-click options

The table below describes the right-click options when you have selected a Mined Out Quantity or Preschedule to display in the Path View:

Option

Description

Insert Block

Opens the Insert Block window so that you can insert a block in the selected path.

Check Entries

Checks records to ensure that there are no errors or warnings in the path (for example, if percentages are logically inconsistent).

Remove Errors

Removes any errors found during the check (for example, if the mined percentage is greater than the released percentage, XPAC recalculates values to display a more logically consistent percentage).

Expanded View

Toggles between an expanded and collapsed view of the path.

Sort

Sort the records that display in the data sheet. Select either:

None to apply no sorting to records that display in the data sheet; or
Database to sort records by descending order from the database tree structure.